The new Florida Gulf Coast University Campus is located in Fort Myers, Florida for THE BOARD OF REGENTS & STATE UNIVERSITY SYSTEM. It is the 10th new campus to join the State University System. The project, although new, provided its own unique challenges. The new campus, totaling 250,000 s.f., consisted of seven (7) new buildings, hard scape, parking and main entrance road. The scope of work included, (commencing at 6 o’clock on the site photo and moving clockwise) the Library / Administration Building, Academic Building #2, Academic Building #1, Student Services Building #2, Student Services #1, the Wellness Center and (off the picture to the south) the Central Energy Plant.
The Central Energy Plant is designed to expand as the campus expands. It is a chilled water system utilizing ice storage as an energy savings for cooling the campus.
Project Challenge:
The project, although new, provided its own unique challenges. The new campus, totaling 250,000 s.f., consisted of seven (7) new buildings, hard scape, parking and main entrance road. The scope of work included, (commencing at 6 o’clock on the site photo and moving clockwise) the Library / Administration Building, Academic Building #2, Academic Building #1, Student Services Building #2, Student Services #1, the Wellness Center and (off the picture to the south) the Central Energy Plant.
The Central Energy Plant is designed to expand as the campus expands. It is a chilled water system utilizing ice storage as an energy savings for cooling the campus.
1999 Associated Builders and Contractors National Award of Excellence – Institutional (over 25M)
2000 “Florida Art in State Buildings” – Selection Committee
Project Details:
Location:
Fort Myers, Florida
Square Footage:
250,000 s.f.
Our Valuable Team Members on this Project:
Project Client
Florida Gulf Coast University
Project Representive
Florida State University System
Project Manager
Brown & Root
Civil Engineer
Post, Buckley, Schuh & Jernigan, Inc.
Structural Engineer
Tilden, Lobnitz & Cooper, Inc.
Electrical Engineer
Tilden, Lobnitz & Cooper, Inc.
Mechanical Engineer
Tilden, Lobnitz & Cooper, Inc.
Plumbing Engineer
Tilden, Lobnitz & Cooper, Inc.
Roofing System
A combination of standing seam metal and single ply
Food Service Consultant
SSA Foodservice Consultants
Project Consultant
Kevin L. Erwin Consulting Ecologist, Inc.